Hi Pete,
I've maintained the work center formula as depicted by you. Still the issue is same.
Also I've checked this in some other system as well still the issue reflecting sameImage may be NSFW.
Clik here to view.
Please check the operation time here. Although the available capacity on work center is 9hr X 5= 45 Man hours, still while scheduling the operation @ rate of 9 hrs/day (means it's not taking no. of capacities into account)
Image may be NSFW.
Clik here to view.
Can you please confirm this in your system ?
if this is correct, then where do the No.of capacity has an impact? how system will take it into account?
Seeking valuable suggestion from other experts also ...
Thanks