Re: Budget at Level 5 WBS

$
0
0

Hi,

 

 

Pavan gupta wrote:

 

 

my quesion in standard do we have any option in directly giving budget at Level 5 only and save, If we do like this system will throw budget exceeded at upper levels of WBS.

 

Firstly I want to tell you that, When you enter budget at level 5 in CJ30 and total-up, then it will consider only to level 5 not for all other.

 

You are facing error because I think after entering budget, you are not performing total-up.

 

Procedure:

 

1)Goto CJ30->Enter Project Definition only not WBS->Press Enter

 

2)Now select your level 5 WBS->Enter Budget->Select Column ->Menubar->Edit->Total-Up

 

Now check & save. This budget will consider to level5 only.

 

Regards

Shishir