Hi all,

 

I had two versions of BOM created for a material which on MRP/MPS run exploded the first version of the same. The problem is i had the first version put to 'Inactive' now and had an MRP/MPS run which obviously i thought would explode the 2nd version of the BOM but it din't.I even tried setting the BOM explosion parameter in MRP 4 view to '1 - BOM selection by explosion date' but even that dint make any difference. Well then when i had the deletion indicator checked for the first BOM version the next MRP/MPS run picked the 2nd version. So is there any settings that i could make other than this deletion flag to have the 2nd version of BOM picked.

 

Is this something because of the validity?

 

Version 1's Validity: 10.01.2014 to 31.12.9999

 

Version 2's Validity: 10.02.2014 to 31.12.9999

 

I don't have the ECM enabled as well so can't literally change the dates.

 

Any help is really appreciated. Thanks in advance.

 

Final Note: Thanks to SCN forum been really helpful for me in most of the cases. And thanks to the forum members as well. Very supportive.

 

Regards,

Rahul